July 2016 Update – 3rd crossing at SCPx installed successfully.
On 06 July 2016, the 880 m long 48″ pipe string was installed under the Turian Chai in Azerbaijan by the SCPx HDD Contractor in a safe and timely manner. Preparations for the rig move...
May 2016 Update – 2nd crossing at SCPx completed.
On May 14 2016 the 710 m long 48″ pipeline under the Geok Chai river was installed by DrillTec, the HDD Sub Contractor on SCPx. All went well and preparations are ongoing to move...
March 2016 Update
It’s mid March and progress has been made at SCPx. The first crossing, the 654 m long 48″ under the Agsu Canal is now installed and site preparations for the next crossing under the...
SCPx Update December 2015
Drilling finally commenced at the Agsu Canal HDD in December. Completion of the crossing is targeted for January 2016. cialis generico en la india Borizontal wishes you a safe end to 2015 and a...
farmaco generico del levitra Unique BuGils FC win over Sabor Latinos
On Saturday 21 November the Borizontal-sponsored BuGils FC claimed a unique but well deserved win over their main nemesis, the Sabor Latinos. where to buy levitra In it’s long history BuGils FC have never...
Primo Marine and Borizontal cooperate
Primo Marine and Borizontal have agreed to cooperate for HDD design and supervision works. Primo Marine, based in Rotterdam, The Netherlands is an independent specialist with a wealth of expertise in subsea cabling and...
BuGils FC near the top of the table
After 3 wins in 4 matches, BuGils FC is 2nd in the table, only behind the new and un-scandinavian Vikings. Well done BuGils FC!
BuGils FC starts the new season in style!
BuGils FC started the 2015 – 2016 season great with back to back wins VS Mollys and Lions. The new kit with Borizontal logo must have made the difference!
SCPx Update August 2015-2
Welding has started on the 52 joints of 20,1 mm 48″ pipe. Drill rig is expected by the first week of September.