It’s mid March and progress has been made at SCPx. The first crossing, the 654 m long 48″ under the Agsu Canal is now installed and site preparations for the next crossing under the Geok Chai Canal are nearly completed. Mobilization to site is expected within this month.

Below some pictures of the Pullback at Agsu Canal as well as of the Site Preparation at Geok Chai.

SCPx-3873

 

DSC04782 DSC04752 DSC04623 DSC04590
SCPx-4093
SCPx-3944 SCPx-3937 SCPx-3931 SCPx-3919 SCPx-3908 SCPx-3904