Late October 2018 Lucas Engineering & Construction completed the pullback of the 2065 m long 24 inch gas pipeline for the above project. The pipe string pull back, with the pipe string welded onboard Saipem’s DLB in 24 m sections, took over a week to complete.
PT Borizontal Sukses Jaya was hired to provide Project Management.